miércoles, 27 de junio de 2012

ANALISIS DE COSTO DE TRACTOR TIPO D7


A N A L I S I S    D E    C O S T O
GASTOS POR EQUIPO MECANICO
EQUIPO MECANICO = TRACTOR SOBRE ORUGAS
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA TRABAJADAS = HM 100.00
SUBTOTAL = S/. 14,000.00
GASTOS POR COMBUSTIBLE POR 100 HM
CONSUMO HORARIO = GAL / HM 7.00
HORAS MAQUINA TRABAJADAS = HM 100.00
CONSUMO TOTAL = GAL 700.00
COSTO POR GALON = S/. 8.51
SUBTOTAL = S/. 5,957.00
GASTOS POR PERSONAL
PENSION ALIMENTICIA =
CANTIDAD DE PERSONAS (OPERADORES) = UND 2.00
DIAS CONSUMIDOS = DIA 20.00
COSTO DIARIO = S/. 10.00
SUBTOTAL = S/. 400.00
MONTO TOTAL POR DEVOLUCION = S/. 6,357.00
CONVERSION A HORAS MAQUINA DEL PETROLEO PROPORCIONADO PARA LAS 100 HM
MONTO TOTAL POR DEVOLUCION = S/. 6,357.00
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 45.41
GASTOS POR COMBUSTIBLE POR 51.49 HM
CONSUMO HORARIO = GAL / HM 7.00
HORAS MAQUINA A TRABAJAR = HM 45.41
CONSUMO TOTAL = GAL 317.87
COSTO POR GALON = S/. 8.51
SUBTOTAL = S/. 2,705.07
CONVERSION A HORAS MAQUINA DEL PETROLEO PROPORCIONADO PARA LAS 51.49 HM
MONTO TOTAL POR DEVOLUCION = S/. 2,705.07
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 19.32
GASTOS POR PERSONAL
PENSION ALIMENTICIA =
TOTAL HORAS MAQUINA A TRABAJAR = HM 19.32
CANTIDAD DE PERSONAS (OPERADORES) = UND 2.00
DIAS CONSUMIDOS (ESTIMADO) = DIA 4.00
COSTO DIARIO = S/. 10.00
SUBTOTAL = S/. 80.00
CONVERSION A HORAS MAQUINA DEL GASTO POR PERSONAL POR LAS 25.04 HM
MONTO TOTAL POR DEVOLUCION = S/. 80.00
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 0.57
TOTAL HORAS MAQUINA A TRABAJAR = HM 65.30
A N A L I S I S    D E    C O S T O
GASTOS POR EQUIPO MECANICO
EQUIPO MECANICO = TRACTOR SOBRE ORUGAS
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA TRABAJADAS = HM 100.00
SUBTOTAL = S/. 14,000.00
GASTOS POR COMBUSTIBLE POR 100 HM
CONSUMO HORARIO = GAL / HM 8.00
HORAS MAQUINA TRABAJADAS = HM 100.00
CONSUMO TOTAL = GAL 800.00
COSTO POR GALON = S/. 8.51
SUBTOTAL = S/. 6,808.00
GASTOS POR PERSONAL
PENSION ALIMENTICIA =
CANTIDAD DE PERSONAS (OPERADORES) = UND 2.00
DIAS CONSUMIDOS = DIA 20.00
COSTO DIARIO = S/. 10.00
SUBTOTAL = S/. 400.00
MONTO TOTAL POR DEVOLUCION = S/. 7,208.00
CONVERSION A HORAS MAQUINA DEL PETROLEO PROPORCIONADO PARA LAS 100 HM
MONTO TOTAL POR DEVOLUCION = S/. 7,208.00
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 51.49
GASTOS POR COMBUSTIBLE POR 51.49 HM
CONSUMO HORARIO = GAL / HM 8.00
HORAS MAQUINA A TRABAJAR = HM 51.49
CONSUMO TOTAL = GAL 411.92
COSTO POR GALON = S/. 8.51
SUBTOTAL = S/. 3,505.44
CONVERSION A HORAS MAQUINA DEL PETROLEO PROPORCIONADO PARA LAS 51.49 HM
MONTO TOTAL POR DEVOLUCION = S/. 3,505.44
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 25.04
GASTOS POR PERSONAL
PENSION ALIMENTICIA =
TOTAL HORAS MAQUINA A TRABAJAR = HM 25.04
CANTIDAD DE PERSONAS (OPERADORES) = UND 2.00
DIAS CONSUMIDOS (ESTIMADO) = DIA 4.00
COSTO DIARIO = S/. 10.00
SUBTOTAL = S/. 80.00
CONVERSION A HORAS MAQUINA DEL GASTO POR PERSONAL POR LAS 25.04 HM
MONTO TOTAL POR DEVOLUCION = S/. 80.00
COSTO ALQUILER HORARIO = S/. 140.00
HORAS MAQUINA A TRABAJAR = HM 0.57
TOTAL HORAS MAQUINA A TRABAJAR = HM 77.10